Cogeneration power plants, biomass fired, turn key projects

  1. Strizivojna HRAST, Croatia, 3,3 MW(el) + 6 MW(th), completed 2010.
  2. BE-TO Glina, Croatia, 1,2 MW(el) + 5 MW(th), completed 2015.
  3. BE Sava, Croatia, 2 MW(el) + 4 MW(th), completed 2017.

 

Biomass and waste fired boiler

Year Plant Contracted Fuel Capacity (t/h) Design pressure (bar) Design temp. (°C)
2017 Stara Gradiška, Croatia BCP Turn-key wood chip, bark, production wood waste 13 40 400
2015 Glina, Croatia BCP Turn-key wood chip, bark, production wood waste 10 35 350
2012 Tanin Sevnica, Slovenia Burning system and boiler retrofit wood waste from production 22,5 45 450
2011 Tyrone, Northern Ireland Boiler delivery waste construction wood 13,7 42 420
2011 Strizivojna HRAST, Croatia BCP Turn-key wood chip, bark, production wood waste 20 40 400
2010 Stramproy, Netherland Boiler delivery wood chip i waste wood 13,5 52 450
2009 Valorbois, Belgium Boiler delivery wood chip 20 55 450
2008 Isabella Plants, Philippines
Two identical boilers
Boiler delivery rice husks 11,5 32 425
2008 Tanin Sevnica, Slovenia Boiler retrofit wood waste from production 22,5 45 450
2007 TO Celje, Slovenia Boiler delivery waste (RDF) 20 36 360
2006 Sulzbach, Germany Boiler delivery forrest biomass 22 55 455